  • How to install a Liquid Nitrogen Freezer?

    I. Preparation Before Installation

     

    1. Site Selection

        • Choose a well-ventilated, dry, flat area with sufficient load capacity to install the liquid nitrogen freezer. Avoid damp, high-temperature, or corrosive environments.
        • Ensure there is enough space around the site for operating, maintaining the equipment, and storing and transporting liquid nitrogen.

    2. Equipment Inspection

        • Before installation, carefully check all parts of the liquid nitrogen quick freezing machine to ensure they are undamaged and complete, with no transport-related damage.
        • Verify that the equipment's model, specifications, and technical parameters match the purchase contract.

    3. Tools and Materials Preparation

        • Prepare the necessary installation tools, such as wrenches, screwdrivers, and pliers.
        • Gather required installation materials, including sealants, washers, and cables.

    4. Safety Gear Preparation

        • Installers should wear appropriate safety gear, such as hard hats, protective gloves, and safety goggles.

     

    II. Installation Steps

     

    1. Positioning the Equipment

    2. Connecting the Liquid Nitrogen Supply Line

        • Connect the liquid nitrogen supply line to the equipment's nitrogen inlet, using suitable seals to ensure a tight, leak-free connection.
        • Before connecting the line, make sure the inside is clean and free of debris.

    3. Electrical Connections

        • Follow the electrical schematic to connect the power cable to the equipment's power interface.
        • Ensure the electrical connections are secure, properly grounded, and meet safety standards.

    4. Installing the Ventilation System

        • If the equipment requires a ventilation system, install it according to the provided instructions to ensure proper airflow and the timely removal of nitrogen gas produced during operation.

    5. System Testing

        •  After completing the installation steps, conduct system testing.
        • Check that all connections are secure and that there are no loose parts.
        • Test the electrical system to ensure it functions correctly.
        • Test the liquid nitrogen supply and freezing system to check the freezing performance and nitrogen usage.
    • liquid nitrogen tank
    • liquid nitrogen pipe
    • induced draft fan
    •  

    III. Post-Installation Inspection and Acceptance

     

    • Visual Inspection: Check the equipment for any damage, deformation, or paint peeling.
    • Leak Check: Use a leak detector or soapy water to check the nitrogen supply line and other connections for leaks, ensuring there are none.
    • Operational Testing: Run the equipment for a while to observe its operation, including temperature control, pressure readings, and operational sounds.
    • Performance Acceptance: Based on the technical parameters and performance indicators, verify the freezing speed and effectiveness to ensure the equipment meets usage requirements.
    • liquid nitrogen quick freezing machine 3000L
    • liquid nitrogen quick freezing machine 3000L
    • liquid nitrogen quick freezing machine 3000L

     

    IV. Precautions

     

    • Follow the installation manual and relevant standards strictly during the installation process; do not change steps or methods without approval.
    • Installers should have the necessary professional knowledge and skills, familiar with the installation process and safety precautions for liquid nitrogen freezers.
    • If any issues or abnormalities arise during installation or testing, stop work immediately, investigate the cause, and resolve the issue before continuing.
    • After installation, provide users with a detailed operating and maintenance manual and offer necessary training.

     

    SPEEDCRYO provides on-site installation services, including:

    • Site inspection, planning, and technical proposal services before equipment purchase;
    • On-site installation, debugging, and trial operation guidance after equipment arrival;
    • On-site operation guidance;
    • Guidance for installing liquid nitrogen tanks and pipelines;
    • Guidance for exhaust pipe installation for the liquid nitrogen freezer.

    If you need our professionals to provide site planning services before purchasing, feel free to contact us; it’s completely free!